Economic Viability
The
investment in the plant is appr. US$ 350,000 equivalent to US$ 1460
per kW. This figure does not include costs of the feasibility study
and designs provided by the Swiss engineers – Technical Assistance
from Switzerland – and the management and supervision inputs by the
investor P.T. Chakra. Usually these costs amount to 10-15% of the
investment.
The
cost breakdown shows the large proportion of the civil works. Costs
of electro-mechanical equipment have been kept relatively low due to
the procurement of the turbines from a local manufacturer.
|
Civil Works
|
47% |
|
Electro-mechanical
equipment |
38% |
|
Transmission lines |
7% |
|
Land acquisition |
1% |
|
Contingencies |
7% |
|
|
100% |
When the project was considered first time in
1999, the price of diesel fuel was around Rp. 600 per litre
(including delivery costs to the estate by bowser). With this price,
the feasibility of the project was still doubtful at that time.
However, in view of future price increases to be expected, the
estate management decided to go ahead with the project.
Figure 1: shows
the diesel fuel price as it was estimated in 2000 in the feasibility
study compared to the actual development till 2002 and future price
increases already announced by the Indonesian Government.
Figure 2: shows the unit cost in
Rupiah per kWh for the electricity of the Minihydro plant (backed up
by diesel genset) as compared to the unit cost of the electricity
produced by diesel genset alone. In addition to the effective unit
cost by the Dewata Minihydro (i.e. based on the actual investment of
US$ 350,000 or US$1460 per kW), the hypothetical cost curves for
higher investment costs of US$ 1500, 2000, 2500 and 3000 per kW are
also given. These figures demonstrate clearly that Minihydro is a
feasible power option even with higher investment cost for those
cases where the conditions are less favorable as in the Dewata
project.
The internal rate of return (IRR) - a measure
indicating the commercial viability of a project - was above 20% for
the Dewata project already in the feasibility study undertaken in
2000, taking a lifespan of the plant of 20 years. It has
substantially improved after calculated on the higher diesel price.
The pay-back period of the investment stands at 5-6 years.
|