On this Page
 
Introduction
 

PLN System Characteristics & Performance

 

Energy Sales & Demand Forecast

 

Average Electricity Tariff

 

Installed Capacity

 

Generation & Transmission Plan 2001 - 2010

 

Investment Requirements for Generation and Transmission 2001 - 2010

 

Java-Bali Power System

 

Deficit Areas

 

Independent Power Producers

 

Primary Energy Mix

 

500 Kv Development in Java-Bali System

 

Sumatra Power Development Plan

 

Java-Sumatra Interconnection

 
East-South Kalimantan Interconnection
 
Electricity in ASEAN Member Countries
 
Brunie Darussalam
 
Cambodia
 
Indonesia
 
Lao PDR
 
Malaysia
 
Myanmar
 
Philippines
 
Singapore
 
Thailand
 
Vietnam
 
 


PLN System Characteristics

& Performance

 

  1999 2000 2001
Production 80.50 84.00  
Transmission      
- Transmission Line ('000 KMS) 24.383 24.822  
- Substation (MVA) 46.964 49.957  
Distribution      
- Medium Voltage Lines ('000 KMS) 207.615 216.220  
- Low Voltage Lines ('000 KMS) 277.955 287.531  
- Substations (MVA) 26.029 27.551  
Number of Employees 53.076 50.301  
Number of Customer (Million) 27.52 28.60  
Total Revenue (Trillion Rp) 15.67 22.14  
Total Assets (Trillion Rp) 73.22 77.99  

 

 

Last Updated : May 9, 2006 3:16 PM